Binh Gia Resident apartments

2015-06-17 03:47:35

Overview scene of Binh Gia Resident apartments

Located in city center, project Binh Gia Resident invested by Ba Ria- Vung Tau House Development joint stock company in purpose of supporting provincial residents’ demand which can be affordable for workers with stable income.

  • High construction: 20 floors and 1 basement.

  • Total floor area: 35,258 m2 (including basement)

  • Basement area: 1,630.5 m2

  • Construction rate: 63%.

  • Land utilization rate: 9.44

  • Total number of apartments: 317

I. BINH GIA RESIDENT APARTMENTS’OVERVIEW SCENE
 

Overview scene of Binh Gia Resident apartments

 

 

II. LAYOUT FLOOR

 

This is the interior arrangement drawing for consulting of some typical apartments of Binh Gia Apartments:

The interior arrangement drawing for consulting of apartment number 01, 08, 09 and 18
The interior arrangement drawing for consulting of apartment number 02 and 05
The interior arrangement drawing for consulting of apartment number 03, 06
The interior arrangement drawing for consulting of apartment number 04
The interior arrangement drawing for consulting of apartment number 07
The interior arrangement drawing for consulting of apartment number 10,11,16 and 17
The interior arrangement drawing for consulting of apartment number 13
The interior arrangement drawing for consulting of apartment number 14

  • THE PROJECT HAS BEEN COMPLETED AND THE APARTMENTS HAVE BEEN HANDED OVER FROM 04/02/2018
  • UPDATE THE PROJECT’S PROGRESS

- Basically finished external paintings, basement parking, lobbies, emergency exit.

-Installed interior, doors, sanitary ware up to the 15th floor.

- Framed elevator systems and continue to complete the installation to make them come into operation.

 

  • UPDATE THE PROJECT’S PROGRESS UP TO OCTOBER, 2017

-   Finished painting, plastering the floors, bricklaying, installing the electric and water system up to the 11th floor.

-   Installed doors,  sanitary ware, basic interior system up to the 9th floor.

-    Promote the progress of finishing the rest floors. Prepare to install elevator system

  • PROGRESS TO THE END OF FEBRUARY:  

    - Finished roughly up to 11th floor

    - Separatingthe apartments up to 6th floor, wall to floor 3

    - Expected to finish roughly in October 2017